Z1900110 – 2X25PL basement OOO STUDENOVSKOYE (Russia)

The project was completed last month and delivered to the customer. It includes a full basement milking parlor, AfiLab, Sort/ Weight, and AfiAct II. Milking has now begun on site.

Z20200031 – Upgrade Rotary 90 GEA (Russia)

Upgrade of a 90 stall GEA rotary parlor should be up & running in Jan 2021. The project includes full Afimilk parlor automation equipment, AfiLabs, Sort/ Weight systems, and AfiAct II system.

Z1900089 – 2*2*30PL – KUBANSKAY STEP (Russia)

This project has just completed the first stage of concrete. The project will include A full Afimilk parlor, AfiLab, Sort/ Weight, and AfiAct II. The next stage will start in two months.

Z20200021 – 2X15 HB – XANTEMIR (Uzbekistan)

This project will include a full Afimilk system, and milk meters. The project is planned to finish towards the end of this year.

Z20200038 -2X20 PLL – Rulikha (Kazakhstan)

This project will include a full Afimilk management system, milk meters, AfiLabs, Sort/ Weight and AfiAct II. It should start the Afimilk equipment installation by the end of this year.

Z1900002/3 – 2x2X25 Parallel basement (Russia) 

These two basement parlors will include a full Afimilk management system, AfiLabs, Sort/ Weight, and AfiAct II. The site is planned to be up and running in the first half of 2021.